Weekly Construction Report
Week of November 21, 2022
RICHLAND COUNTY (November, 2022) – The following construction projects are anticipated to affect highways in Richland County next week. All outlined work is weather permitting.
U.S. Route 30 major rehabilitation – U.S. 30, from State Route 309 to just east of the 5th Avenue ramps, will have lane closures for a major rehabilitation project. Traffic will always be maintained.
NEW IMPACTS
- On Tuesday, November 22, crews will open the second lane of traffic for U.S. 30 westbound between 5th Avenue and Bowman Street. This will be the final traffic switch into the permanent pattern.
- Resurfacing work will resume in the spring.
CONTINUING IMPACTS
- Traffic on U.S. 30 eastbound, from just west of SR 309 to 5th Avenue, has been switched into its permanent traffic pattern.
- Traffic on U.S. 30 westbound, between Bowman Street and SR 309, has been switched into its permanent traffic pattern.
- Motorists have access to all eastbound and westbound exit and entrance ramps.
Estimated completion of entire project: May 2023